Contech House - Completed May 2012  

This project involved the demolition of a large fire damaged industrial unit. The building was of steel framed construction, with metal profiled cladding. 
 
The building being demolished had sustained substantial fire damage, internal walling was in an unstable condition, as was an element of the roof. 
 
There were live overhead cables approximately 3m above the roof of the building. 
 
With careful planning and safe methods of work implemented, the demolition was completed without any problems. 
 
This project was finished on time and within budget...click on an image to view...